Thursday, March 13, 2014

Irrigation update



The irrigation project / addition to holes 6 and 7 is moving along very nicely.  After a rocky start to the first half of the trenching, we got all the trenches cleaned out, the pipe, swingjoints, and heads installed, and all the wires ran.

Clean trench - ready for pipe
Rolling out wires
Keeping all the wires organized
We have completed the back fill and sodding of the first part.

Backfilling with a tractor bucket

                         Trenches back filled and ready for compaction


Compacting
Compacted trench

Sod going down, rolled up for 1.5 weeks and started to yellow a little
After the first phase was almost completed we went and opened up the second half.
The sod is rolled up, trenching is complete, and now it is time to start all the installation of pipe.
Sod being rolled up

Trenching



Phase 2 - 8,000 ft of pipe, 10,000 ft of wire, about 50 more heads 

A clean trench
Overview of the second half

The second part with pipe installation in progress
We also have base set for the new satellite that will control all of the new additions.
Base is ready wires and new satellite

Old pipe that is cut through by the trencher needs to be repaired
The old wires are being cut through and ignored because we will be re-wiring all heads on the two holes.  It is amazing that the wires are only about 2-3 inches deep.  This kept us from performing all the proper cultural practices that the turfgrass needs like aerification.

Shallow wires
Equipment being used